Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Project Management

Dee View House

Trident’s Liverpool office was appointed by Dee View House Management Company Ltd as lead consultant for structural repair works to Dee View House, Wirral. The project was successfully completed in December 2019, on budget and on programme.

The project involved organising a design team for compiling tender costs and liaising with the client to agree a settlement from National House Building Council (NHBC).

Historically, the residents of the building had noticed hairline cracking within the external walls which were raised with the NHBC. The NHBC stated these were due to thermal movement and the residents continued living in the building unaware of a design flaw in the property.

In 2018, a steel lintel collapsed in a window opening. When the building was constructed the detailing in design and construction at the point of the failure was poor.

Trident liaised with a structural engineer to formulate a repair method which included jacking up displaced steel beams the floors affected by the collapse. The engineers design was incorporated into a package of works to include remedial works internally and externally.

Trident Building Consultancy project managed the works which were completed on time and within the budget constraints of the offer made by NHBC to repair the works.

Client
Dee View House Management Company Ltd
Sector
Residential
Our Role
Key Issues
  • Structural failure
  • Water ingress into property due to openings within the external fabric following the structural collapse
  • 4 of the 6 flats in the property were occupied at the time the works were required
  • Authorised costs required by NHBC prior to client instructing the remedial works